::: Imperial :::
Register Login
 
 
 
 
Project (Procurement & Contracts)
 
 
You are here: Project Procurement Services * Projects Undertaken * Solwara 1 (Subsea Minerals)   Search
Solwara 1 (Subsea Minerals)

June 2007 to November 2007

Hatch and Associates - Nautilus Mineral, Solwara 1 project Papua New Guinea

Logcon where engaged by Hatch to:

  • Undertake the design and write a Supplier Prequalification process for the project for use on Major Procurement packages. Typical value of these packages ranged from $2 Million (Agitators) up to $20 Million.
  • Undertake the design and write Request For Tender ("RFT) documents and procedures for Major Procurement packages ranging from $2 Million (Agitators) up to $20 Million per package.
  • Manage major tender packages: RFT, Notices, Tender Opening, Evaluation and Recommendation.
  • Average value of package were $10 Million each including Rod and Ball Mill, Filter Press, Thickener, Flotation Cells and Regrind Mills.

Proceed to Nautilus Minerals Web site: http://www.nautilusminerals.com/s/Projects-Solwara.asp

 
 
 
 
Privacy Statement  |  Terms Of Use
Copyright 2010 Logistics Consulting ABN: 71 089 159 231
 
   
  Boggo Road Busway Alliance (Busway) | Aurukun (Bauxite) | Solwara 1 (Subsea Minerals) | Strategic Procurement (Logistics and Heavy Haul) | Toms Gully Mine (Gold) | Gunung Bayan (Coal) | Procurement Study (Cotton) | Coal Handling Plants (Procurement Systems) | Broadcasting and Telecommunications | Kinleith Modernisation (Pulp and Paper) | Olympic Dam Expansion (Copper Uranium) | BOC 600 MTPD ASU (Oil and Gas) | Phosphate Hill (Process Plant) | Strategic Procurement and Project Management | Thermal_Geothermal and Power Stations